A new tender for the first phase of the road network within the Akamas National Forest Park was officially launched on 6 November 2026, setting the stage for construction work to resume in February 2027 after being suspended since December 2023. The contract carries an estimated budget of 5.63 million euros, rising to 6.694 million euros including VAT. With construction planned over a 13-month timeline, completion is targeted for 28 February 2028. Tender submissions are due on 8 December 2026 and will be opened the same day before the relevant evaluation committees. The long-awaited project is crucial for managing the protected area, which receives more than 400,000 visitors each year. Since work was halted, the incomplete road network has suffered from safety, drainage, and maintenance issues, while delaying the full enforcement of park protection controls.
Phase A focuses on upgrading three key roads totaling approximately 9.9 kilometres along with an organized parking facility in the Lara area to stop uncontrolled parking on delicate ecosystems. Road 1A stretches 6.2 kilometres from Aspros Potamos to Toxeftra and Lara, serving as the main access route to the Lara coast. Road 2 is a 2.7-kilometre ring road designed to reduce traffic around the sensitive turtle protection zone, while Road 4Bi covers 1.0 kilometre from Toxeftra to Avakas to provide safe access to the Avakas gorge. Construction will be governed by strict seasonal bans to safeguard sea turtle nesting and bird breeding activities. Funding is co-financed, with 60 per cent coming from the EU THALIA 2021-2027 Cohesion Policy Programme and 40 per cent from national funds. Consequently, physical delivery will be monitored by the Control Directorate of the Ministry of Transport, Communications and Works, while the Treasury manages financial certification for the EU.
The project originally began on 27 October 2022 but was suspended on 11 December 2023 when only 17.67 per cent of the physical work had been completed despite 94 per cent of the contract timeframe having elapsed. Environmental groups, including Terra Cypria, BirdLife Cyprus, the Cyprus Wildlife Society, the Initiative for the Rescue of Natural Coasts, and the Federation of Environmental Organisations of Cyprus, had raised alarms over serious breaches of environmental conditions. Following cabinet decisions on 20 December 2023 and 11 March 2024, the government ordered a redesign with a smaller footprint and enhanced protection terms. A supplementary assessment in 2024 and a 2025 environmental authority compliance report finalized the new parameters. Financial disputes with the previous contractor were settled amicably with advice from the Law Office of the Republic and approval from the Finance Ministry. Modified construction drawings were approved on 31 July 2026, and environmental criteria were integrated directly into contractual requirements on 30 September 2026.
Full implementation across all phases and infrastructure in the Akamas park is scheduled for completion by 15 November 2028, followed by a 12-month defects liability period. Urgent safety works on the forest road from Baths of Aphrodite to Fontana Amorosa, budgeted at 160,000 euros, began on 9 November 2026 to ensure fire engines and emergency vehicles can navigate the terrain safely, with safety barriers expected by mid-December. Tendering for visitor information hubs was launched on 24 August 2026, with the Department of Forests currently evaluating a single bid. Subsequent development phases will follow, including Phase B running from 1 November 2026 to 15 November 2028, Phase C from 1 January to 1 August 2028, the closure of irregular access points by 30 September 2028, and systematic habitat restoration once Phase A construction concludes.